March/April 2020
- All asphalt and stripping is completed for taxiways and parking lot
- Signage, casework, flooring, landscaping, and interior finishings completed
- Certificates of Occupancy are received in middle of Corona Virus pandemic
- Tenants take possession of storage hangars at 100% occupancy
- Keys are received from General Contractor NDL with proper social distancing
- Lone Mountain Aviation and All In Aviation are OPEN FOR BUSINESS at 1456 Jet Stream Dr
- Signage, casework, flooring, landscaping, and interior finishings completed
- Certificates of Occupancy are received in middle of Corona Virus pandemic
- Tenants take possession of storage hangars at 100% occupancy
- Keys are received from General Contractor NDL with proper social distancing
- Lone Mountain Aviation and All In Aviation are OPEN FOR BUSINESS at 1456 Jet Stream Dr
February 2020
- Taxiway paving is completed amongst all T & Box Hangars
- Electric, Gas, AC, Swamp Coolers, sewer and other utilities are connected
- Exterior paint is completed while marquee installation begins
- Grading, valley gutters, parking lots, sidewalks & curbs are in process around maintenance/office building
- Scaffolding disassembly begins after stucco along Jet Stream Dr is completed
- Interior paint is complete while electrical light/outlet ops checks are conducted
- Electric, Gas, AC, Swamp Coolers, sewer and other utilities are connected
- Exterior paint is completed while marquee installation begins
- Grading, valley gutters, parking lots, sidewalks & curbs are in process around maintenance/office building
- Scaffolding disassembly begins after stucco along Jet Stream Dr is completed
- Interior paint is complete while electrical light/outlet ops checks are conducted
January 2020
- Surveying, grading, sub grade install, & gravel are laid in final preparation for taxiways between storage hangars
- Insulation and drywall installation is completed
- Bathroom flowing and wall wainscot install commences
- Fire riser room plumbing, backup pumps & foam tank are installed
- Exterior glass on buildings installed
- Interior wall texture, paint lighting & ceiling grids begin installation
- Insulation and drywall installation is completed
- Bathroom flowing and wall wainscot install commences
- Fire riser room plumbing, backup pumps & foam tank are installed
- Exterior glass on buildings installed
- Interior wall texture, paint lighting & ceiling grids begin installation
December 2019
- Valley gutter installation and taxiway grading begins
- Fire risers, pumps, monitors & sprinklers near completion
- Stucco on Box hangars commences while sheet metal and insulation nears completion
- Steel studs are installed, drywall application begins and wall insulation is inserted
- Exterior paint on maintenance building is applied
- Rough plumbing is completed
- Switch gear is installed, power cords are pulled in preparation for Nevada Power service
- Building column fire protection begins
- Fire risers, pumps, monitors & sprinklers near completion
- Stucco on Box hangars commences while sheet metal and insulation nears completion
- Steel studs are installed, drywall application begins and wall insulation is inserted
- Exterior paint on maintenance building is applied
- Rough plumbing is completed
- Switch gear is installed, power cords are pulled in preparation for Nevada Power service
- Building column fire protection begins
November 2019
- All storage hangars are 100% pre-leased & wait list deposits begin to be accepted
- Mezzanine, second story flooring concrete is poured
- HVAC & associated ducting is installed in maintenance & office building
- Walls & insulation are installed in T-Hangar end cap storage & customer bathroom area
- Fire sprinkler system begins installation in maintenance & office building
- Steel studs installation commences on maintenance & office building
- Sheet metal is nears completion on all T-Hangars, Box Hangars & hangar doors
- Underground containment tank is completed & primer paint is applied to maintenance & office building
- Mezzanine, second story flooring concrete is poured
- HVAC & associated ducting is installed in maintenance & office building
- Walls & insulation are installed in T-Hangar end cap storage & customer bathroom area
- Fire sprinkler system begins installation in maintenance & office building
- Steel studs installation commences on maintenance & office building
- Sheet metal is nears completion on all T-Hangars, Box Hangars & hangar doors
- Underground containment tank is completed & primer paint is applied to maintenance & office building
October 2019
- T-Hangars start installing insulation, sheet metal, steel studs, electrical, roofing & trim
- First Box hangar is erected
- Underground foam containment tank construction commences
- Maintenance & office building mezzanine columns & beams begin erection
- North Box Hangar cluster have footings, curbs & slabs formed
- Schweiss hangar door installation begins on Box Hangars
- Mezzanine deck, second story, begins to be erected
- First Box hangar is erected
- Underground foam containment tank construction commences
- Maintenance & office building mezzanine columns & beams begin erection
- North Box Hangar cluster have footings, curbs & slabs formed
- Schweiss hangar door installation begins on Box Hangars
- Mezzanine deck, second story, begins to be erected
September 2019
- South Box hangar cluster concrete footings, slabs & curbs are poured
- Sack & patching commences on concrete tilt panel maintenance & office building
- Columns & beams are erected in the maintenance & office building and secured to tilt panels
- South T-Hangar cluster metal buildings begin erection
- North T-Hangar cluster begins sheet metal, hangar door, electrical conduit, & insulation installation
- Sack & patching commences on concrete tilt panel maintenance & office building
- Columns & beams are erected in the maintenance & office building and secured to tilt panels
- South T-Hangar cluster metal buildings begin erection
- North T-Hangar cluster begins sheet metal, hangar door, electrical conduit, & insulation installation
August 2019
- Existing taxiway asphalt is "milled" to allow for new grading and valley gutter
- South T-Hangar cluster footings, curbs & slabs are poured - Metal buildings begin on site delivery - North T-Hangar columns & beams begin erection - Concrete tilt panels on Maintenance/Office building are poured, stood & secured - Underground electrical is installed throughout site - South Box hangar cluster begins rebar forming |
July 2019

- "Curbs" are formed & poured on north T-Hangar cluster
- Slab for maintenance hangar is poured at night due to temperature
- Forming of concrete tilt panels gets underway
- South RCP underground storm drain is installed
- Backfill dirt is imported for Box hangar pads along JetStream
- Fire hydrants are installed
- Slab for maintenance hangar is poured at night due to temperature
- Forming of concrete tilt panels gets underway
- South RCP underground storm drain is installed
- Backfill dirt is imported for Box hangar pads along JetStream
- Fire hydrants are installed
May/June 2019
- Setup construction perimeter with aviation "Lo-Pros", necessary gates / fencing, work trailer, water stand, etc.
- Grading of site and import of 25,000 yards of fill gets underway
- Underground wet utilities (sewer & water) begin installation
- Off-site tie-ins under JetStream Dr are completed
- 13 Building permits issued by City of Henderson for full construction to commence
- Average 45-50 construction workers on site daily for various trades
- CMU retaining wall and Box Hangar pier footings are erected along JetStream Dr
- Rebar reinforcements and concrete forms are constructed in anticipation of footings and pads being poured
- Only 3 Box hangars remain available for pre-lease
- Metal buildings ordered and inserted into fabrication and production schedule
- Grading of site and import of 25,000 yards of fill gets underway
- Underground wet utilities (sewer & water) begin installation
- Off-site tie-ins under JetStream Dr are completed
- 13 Building permits issued by City of Henderson for full construction to commence
- Average 45-50 construction workers on site daily for various trades
- CMU retaining wall and Box Hangar pier footings are erected along JetStream Dr
- Rebar reinforcements and concrete forms are constructed in anticipation of footings and pads being poured
- Only 3 Box hangars remain available for pre-lease
- Metal buildings ordered and inserted into fabrication and production schedule
March/April 2019

- 2 Parcels are successfully merged and new APN is assigned by CC Assessors Office
- Amended Fire Protection Report completed by Fire Protection Engineer
- Revised architectural and “MEP" plans submitted to City of Henderson
- Revised civil engineering plans submitted to City of Henderson
- Received “Notice to Proceed” with construction from Department of Aviation
- Form 7460’s filed with FAA for building and construction crane heights
- Utility designs commence with: Nevada Energy, Southwest Gas, Cox/Century Link
- Amended Fire Protection Report completed by Fire Protection Engineer
- Revised architectural and “MEP" plans submitted to City of Henderson
- Revised civil engineering plans submitted to City of Henderson
- Received “Notice to Proceed” with construction from Department of Aviation
- Form 7460’s filed with FAA for building and construction crane heights
- Utility designs commence with: Nevada Energy, Southwest Gas, Cox/Century Link
February 2019

- Revised parcel map completed and filed with Clark County Recorder & Assessor's office
- DOA, owner & general contractor pre-construction meeting completed
- Construction trailer put onsite in anticipation of upcoming construction
- City of Henderson replied to building permit application with request for revisions
- DOA, owner & general contractor pre-construction meeting completed
- Construction trailer put onsite in anticipation of upcoming construction
- City of Henderson replied to building permit application with request for revisions
January 2019
- Southwest Gas Corporation repositions natural gas line to accommodate hangar buildings
- Civil improvement & parcel map approved and submitted for official recording
- 100% architectural plans submitted to Department of Aviation & City of Henderson for review
- Addresses for all hangar buildings issued
- Application for building permit & associated fees remitted to City of Henderson
- Civil improvement & parcel map approved and submitted for official recording
- 100% architectural plans submitted to Department of Aviation & City of Henderson for review
- Addresses for all hangar buildings issued
- Application for building permit & associated fees remitted to City of Henderson
Nov/Dec 2018

- Mechanical, Electrical, Plumbing & Fire Protection contracts awarded
- Current HND hangar owners/tenants notified of construction plans & impact
- Construction safety & phasing plans coordinated with DOA
- Grading permit granted from City of Henderson to begin "dirt work"
- Final Fire Protection Report completed by Fire Protection Engineer
- Scheduling of Southwest Gas natural gas line relocation complete
- Current HND hangar owners/tenants notified of construction plans & impact
- Construction safety & phasing plans coordinated with DOA
- Grading permit granted from City of Henderson to begin "dirt work"
- Final Fire Protection Report completed by Fire Protection Engineer
- Scheduling of Southwest Gas natural gas line relocation complete
Sept/Oct 2018
- T-Hangars become 100% committed, secured with deposit and pre-lease, 5 Box hangars remain available
- Held ceremonial ground breaking Oct 12, 2018 with clients, family, industry partners, lease holders & dignitaries
- Civil plans, grading permit & parcel map applications submitted to City of Henderson
- Architectural & Structural plans reach 90% complete
- Sub-contracts begin to be awarded for design/build trades involved, to incorporate plans into final architectural plans
- General Contractor & Department of Aviation work to address construction phasing plan to minimize impact of airport
- Held ceremonial ground breaking Oct 12, 2018 with clients, family, industry partners, lease holders & dignitaries
- Civil plans, grading permit & parcel map applications submitted to City of Henderson
- Architectural & Structural plans reach 90% complete
- Sub-contracts begin to be awarded for design/build trades involved, to incorporate plans into final architectural plans
- General Contractor & Department of Aviation work to address construction phasing plan to minimize impact of airport
August 2018
- Deposit made with Erect-A-Tube metal building company for 16 T hangars
- Relocation of natural gas line in conflict with new building plans scheduled with Southwest Gas Corporation
- Comments from DOA on architectural review are being addressed in preparation for submittal to City of Henderson
- Begin coordinating plans with Department of Aviation for a ground breaking event/celebration
- Request for formal bid are sent to sub-contractors for Mechanical, Plumbing & Electrical
- Relocation of natural gas line in conflict with new building plans scheduled with Southwest Gas Corporation
- Comments from DOA on architectural review are being addressed in preparation for submittal to City of Henderson
- Begin coordinating plans with Department of Aviation for a ground breaking event/celebration
- Request for formal bid are sent to sub-contractors for Mechanical, Plumbing & Electrical
July 2018
- Deposit made to RIGID Steel for metal building materials & structural design for 9 box & maintenance hangars
- Deposit made to Schweiss doors for 9 box & maintenance hangars
- Civil improvement plans in final review at DOA with fire suppression plans made
- Architectural plans submitted to DOA
- Construction site safety plans and temporary fencing proposal submitted to DOA
- Attended EAA AirVenture Oshkosh to meet with industry partners and aviation construction vendors
- Deposit made to Schweiss doors for 9 box & maintenance hangars
- Civil improvement plans in final review at DOA with fire suppression plans made
- Architectural plans submitted to DOA
- Construction site safety plans and temporary fencing proposal submitted to DOA
- Attended EAA AirVenture Oshkosh to meet with industry partners and aviation construction vendors
June 2018
- Civil improvement plans submitted to DOA. Revised site plan requested to expand existing taxiway width. 2 box hangars eliminated, 4 T-hangars added as a result
- Traffic study submitted to City of Henderson
- Request for relocation of gas line submitted to Southwest Gas
- Traffic study submitted to City of Henderson
- Request for relocation of gas line submitted to Southwest Gas
May 2018
- Drainage study approved by City of Henderson. Submitted for concurrence with Clark County Department of Aviation and water authority
- CATEX application filed with FAA
- Parcel merger complete
- City of Henderson requires completion of a traffic study
- T-Hangars reach 100% pre-lease occupancy
- CATEX application filed with FAA
- Parcel merger complete
- City of Henderson requires completion of a traffic study
- T-Hangars reach 100% pre-lease occupancy
April 2018
- Drainage study of property under final review at City of Henderson allowing for full completion of architectural & engineering
- Reached 70% pre-lease occupancy
- Commercial appraisal completed satisfactorily
- Environmental Phase 1 Inspection completed satisfactorily
- Parcel merger map submitted to COH for final review/approval
- Reached 70% pre-lease occupancy
- Commercial appraisal completed satisfactorily
- Environmental Phase 1 Inspection completed satisfactorily
- Parcel merger map submitted to COH for final review/approval
February 2018
- Hosted Cirrus Aircraft, 200+ clients, partners & media at our VGT location to showcase Cirrus SF50 jet, current business and share expansion plans
- Las Vegas Review Journal published piece featuring plans, www.reviewjournal.com/local/henderson/raiders-could-boost-companies-expanding-at-henderson-airport/ - NFL Raiders complete land purchase across street from hangar development - Aviation International News posted online article about HND expansion plans, www.ainonline.com/aviation-news/business-aviation/2018-02-13/aviation-firms-partner-vegas-area-hangars |
January 2018

- Received design approval from City of Henderson
- Reached 35% pre-lease occupancy
- City of Henderson approves land sale to NFL Raiders across street
- Reached 35% pre-lease occupancy
- City of Henderson approves land sale to NFL Raiders across street
December 2017
- Submitted design review for official consideration by City of Henderson and received initial comments before New Years
November 2017
- Revised site plan to accommodate Fire Code requirements (removed Shades, added 1 Box hangar)
- Presented plans to City of Henderson building department
- Presented plans to City of Henderson building department
October 2017
- Launch www.hndhangars.com.
- Begin accepting leases for storage hangars.
- Visit with Henderson mayor Debra March and economic development director Barbra Coffee about expansion plans.
- Finalize plans for maintenance & flight training building.
- Begin accepting leases for storage hangars.
- Visit with Henderson mayor Debra March and economic development director Barbra Coffee about expansion plans.
- Finalize plans for maintenance & flight training building.
November 2016
Clark County Department of Aviation informed us our concepts were approved, and we had an “Agreement in Principle”
Clark County Department of Aviation informed us our concepts were approved, and we had an “Agreement in Principle”
April 2016
Kenny Scherado of Lone Mountain Aviation, a full service aircraft maintenance & avionics shop, and Paul Sallach of All In Aviation/Lone Mountain Aircraft Sales, a pre-owned aircraft sales specialist & Cirrus training center agree to actively pursue plans of expanding current operations from the North Las Vegas airport (KVGT) to the Henderson Executive airport (KHND). |